Quick answer
A 150 kVA generator delivers between 109 kW and 124 kW of three-phase power on its prime rating, depending on the model. The Cummins C150D5 is 150 kVA standby and 136 kVA prime (109 kW), while the C170D5 and C170D5Q are 170 kVA standby and 155 kVA prime (124 kW). That is enough for a food factory, a school or college, a large farm or a warehouse, provided large motors start in sequence and you keep about 20% headroom. Plan around the prime kW rating, keep typical load under about 87 kW on the C150D5 or 99 kW on the C170D5 and C170D5Q, and step up to 200 kVA beyond that.
It is also a size where the label hides a 15 kW difference. The "150 kVA" category in our range contains sets that deliver 109 kW and sets that deliver 124 kW on prime, so the headline kVA is not enough to size from. This guide uses datasheet figures from the 150 kVA generators in our range to show what each can run, with worked examples and the limits to watch. For the size below, see our guide to what a 60 kVA generator can run, and browse our 100 kVA generators too.
What does 150 kVA actually mean?
kVA measures apparent power, while most equipment is labelled in kW. On a three-phase set, multiply kVA by the power factor of 0.8: 150 kVA × 0.8 = 120 kW. Plan around kW on the prime rating, not the kVA on the label.
Three models in our 150 kVA range show how the ratings differ:
| Model | Standby rating | Prime rating | Built in |
|---|---|---|---|
| Cummins C150D5 | 150 kVA / 120 kW | 136 kVA / 109 kW | India |
| Cummins C170D5 | 170 kVA / 136 kW | 155 kVA / 124 kW | India |
| Cummins C170D5Q | 170 kVA / 136 kW | 155 kVA / 124 kW | Europe |
All three supply 400 V, 50 Hz three-phase power through a four-pole circuit breaker, use a Stamford alternator and a 6BTAA5.9 Cummins engine, and are supplied in a silent canopy.
- The category holds two ratings. On the C150D5, 150 kVA is the standby rating. The C170D5 and C170D5Q sit in the same category but are 155 kVA prime, about 15 kW more than the C150D5.
- Standby is for emergencies only. Plan around the prime figure if you will run the set regularly.
- Full-load current is 217 A per phase on the C150D5 and 246 A on the C170 sets, both at the standby rating. At prime it works out at about 197 A and 224 A (calculated).
> Expert tip: When comparing "150 kVA" listings, check the kW on the prime rating. The gap between 109 kW and 124 kW is enough to decide whether a whole refrigeration plant restarts cleanly.
For the full explanation of standby and prime, including the 200-hour and 70% average-load guidelines in ISO 8528-1, see our guide to standby versus prime rating on a 500 kVA generator, which applies at any size, or our general guide to prime versus standby power.
Three phase, single-phase loads and motor starting
On a three-phase generator, single-phase equipment draws from one phase only. A 155 kVA prime rating splits to about 52 kVA per phase, or around 225 A at 230 V, so spread single-phase circuits evenly across the phases.
Why starting loads matter
Refrigeration compressors, pumps, fans and production motors draw several times their running current as they start. As a rough guide, a motor started direct-on-line should be no more than about a third of the generator's kW rating. That is about 36 kW on the 109 kW prime rating and 41 kW on 124 kW. Soft starters, star-delta starters or variable speed drives allow larger motors, and the alternator's motor-starting capability decides the real limit, so ask for the motor-starting curve if you have large machines.
What can a 150 kVA generator run in a food factory?
Food production depends on uninterrupted power, because chilled stock starts warming the moment refrigeration stops and traceability records stop logging. We supplied a Cummins C170D5Q to a Doncaster food manufacturer for emergency standby power, and the case study lists the loads it protects: cookers, chillers, freezers, mixers, packing lines, fire detection, emergency lighting, extraction, ventilation and access control. It notes that the 170 kVA rating gives useful headroom for the inrush currents drawn when compressors, motors and drives restart together.
Typical running loads for a site like this:
| Equipment | Typical running load | Notes |
|---|---|---|
| Refrigeration compressors | 10 to 20 kW each | Priority load, starting surges |
| Production line motors | 20 to 40 kW | Start in sequence |
| Packing lines | 15 to 30 kW | Can often be shed first |
| Extraction and ventilation | 8 to 15 kW | Safety critical |
| Lighting | 10 to 20 kW | Steady load |
| Fire, security and access control | Under 5 kW | Always include these |
| Offices and IT | 5 to 15 kW | Keep on a stable supply |
A worked example. Three 15 kW refrigeration compressors (45 kW), 25 kW of packing lines, 10 kW of extraction, 12 kW of lighting, 3 kW of fire and security systems and 8 kW of offices and IT total 103 kW. That is about 83% of the 124 kW prime rating on a C170 set and about 76% of its 136 kW standby rating. On the C150D5 it is 94% of prime and 86% of standby, which is too tight. The example shows why the model matters as much as the headline size.
What can a 150 kVA generator run in a school, college or large building?
| Load | Typical running load | Notes |
|---|---|---|
| Lighting | 15 to 30 kW | Steady load |
| Heating pumps and boiler controls | 8 to 15 kW | Keeps heating running |
| Kitchen (refrigeration plus cooking) | 25 to 45 kW | Cooking cycles on and off |
| IT, servers and comms | 10 to 20 kW | Critical, constant |
| Lifts | 8 to 15 kW | Starting surge |
| Ventilation | 8 to 15 kW | Steady load |
| Fire, security and access control | Under 5 kW | Always include these |
A worked example. Lighting (20 kW), heating pumps (10 kW), a kitchen (30 kW), IT (12 kW), lifts (8 kW), ventilation (8 kW) and fire and security (3 kW) total 91 kW. That is about 73% of 124 kW prime and 83% of 109 kW. A full commercial kitchen on top of this would not fit.
What can a 150 kVA generator run on a large farm?
Farm loads are dominated by motors and refrigeration, so starting order matters as much as the total. A large dairy with a 7.5 kW vacuum pump, two 7.5 kW milk cooling compressors, a 6 kW water heater, a 2.2 kW wash pump, a 4 kW feed auger, 3 kW of lighting, 5 kW of ventilation and a 15 kW grain dryer fan comes to about 58 kW, which is 47% of the 124 kW prime rating. That leaves comfortable room for growth. Size from the equipment rating plates rather than a generic figure, and start the vacuum pump and milk cooling first.
> Expert tip: Start loads in a fixed order, with the largest motors first and the refrigeration compressors staged, rather than letting everything restart at once when the power returns. The generator ATS installation guide explains how transfer equipment can support that.
What a 150 kVA generator will not run comfortably
- A whole site with several large chillers, lifts and a full commercial kitchen all at once.
- A motor above about 36 to 41 kW started direct-on-line.
- Several large motors starting at the same moment.
- Large single-phase loads concentrated on one phase.
- Continuous running at close to 100% load with no headroom.
How to size a 150 kVA generator for your site
- List everything that must keep running. Be strict and include only essentials.
- Find each running load on the rating plate, in kW or amps.
- Identify the largest starting load and check its starting method.
- Decide standby or prime from how many hours a year the set will run.
- Add 20 to 25% headroom, keep the typical load under about 80% of the prime kW, and check the average over 24 hours stays under 70% of prime.
Eighty per cent of prime is about 87 kW on the C150D5 and 99 kW on the C170D5 and C170D5Q. Seventy per cent is about 76 kW and 87 kW. Our guide to sizing a generator around critical loads explains how to build the load list, and our guide to optimising generator load profiles explains why running very lightly loaded causes problems.
> Not sure your load list adds up? Send us your equipment list, your largest motor and how often the generator will run, and we will check it against a set from stock. Use the contact page or call +44 1302 700200.
150 kVA or 200 kVA?
Stay at 150 kVA if your realistic load is under about 87 kW (C150D5) or 99 kW (C170 sets). Above that, or with large motors to start, look at a 200 kVA generator, which gives 160 kW on its prime rating on our Cummins sets. If your load is much smaller, a 100 kVA set may suit. It is almost always better to size correctly at the start than to replace an overworked set later.
Fuel use and run times
The Cummins C170 D5 datasheet gives fuel consumption at each load on both ratings. Run time depends on the tank: 448 litres on the C170D5 and C150D5, and 400 litres on the C170D5Q.
| Load (prime) | Output | Fuel use | 448-litre tank | 400-litre tank |
|---|---|---|---|---|
| 25% | 31 kW | 12.1 litres per hour | About 37.0 hours | About 33.1 hours |
| 50% | 62 kW | 20.0 litres per hour | About 22.4 hours | About 20.0 hours |
| 75% | 93 kW | 30.6 litres per hour | About 14.6 hours | About 13.1 hours |
| 100% | 124 kW | 36.0 litres per hour | About 12.4 hours | About 11.1 hours |
At the standby rating the datasheet shows 15.2, 23.2, 31.5 and 39.6 litres per hour. The product pages list slightly different full-load figures: 31.2 litres an hour and 14.4 hours for the C150D5, 36 litres an hour and 12.4 hours for the C170D5, and 37 litres an hour and 10.8 hours for the C170D5Q. Run times use nominal tank capacity, so allow a reserve in practice. Our guide to how to calculate generator runtime shows how to work out your own figures.
If your site needs longer autonomy, we supply separate free-standing fuel tanks. Tank size matters for compliance too, because the oil storage rules apply to business containers of 201 litres or more, and all of these sets have bigger base tanks. Check whether they apply to your installation using the GOV.UK guidance on oil storage.
Standby, prime and how it starts
Warranty cover reflects the duty. On all three Cummins models it is two years or 500 hours for standby, and one year with unlimited hours for prime.
The C150D5 and C170D5 use the Cummins PowerCommand 1.2 controller. The C170D5Q uses the PowerStart 0600, and its product page lists automatic mains failure functionality, remote start and stop, fault logging, low fuel warnings and Modbus communications. For a standby generator that must start without anyone on site, the generator, the mains supply and the changeover equipment must be designed as one coordinated system.
Size, weight and noise
| Specification | Cummins C150D5 | Cummins C170D5 | Cummins C170D5Q |
|---|---|---|---|
| Length × width × height | 3,460 × 1,090 × 2,387 mm | 3,460 × 1,090 × 2,387 mm | 3,100 × 1,185 × 1,950 mm |
| Dry weight | 2,390 kg | 2,390 kg | 1,891 kg |
| Wet weight | 2,400 kg | 2,400 kg | 1,973 kg |
| Fuel tank | 448 litres | 448 litres | 400 litres |
| Canopy noise | 76 dB(A) at 1 m | 79 dB(A) at 1 m | 79 dB(A) at 1 m / 68 dB(A) at 7 m |
The European-built C170D5Q is about 500 kg lighter and 360 mm shorter, which can matter for access and lifting. The 1 m and 7 m noise figures are not directly comparable, so read our guide to how quiet a silent generator really is before choosing, or browse our silent generators.
Safety and regulations
- Connection and earthing. The HSE's electrical safety guidance covers the general principles of working safely with electricity. Connection should be made through a changeover arrangement fitted by a qualified electrician.
- Ventilation and exhaust. Diesel exhaust contains carbon monoxide. Never run a generator indoors or in an enclosed space.
- Environmental permits. GOV.UK says specified generator controls apply, unless excluded, to generators with a rated thermal input between 1 MWth and 50 MWth, and generators on the same site are aggregated. As a rough estimate, the datasheet fuel figures of 36 and 39.6 litres per hour at about 10 kWh per litre give around 0.36 and 0.40 MW for one set, well below the threshold. If you have several generators on a site, check the total in the GOV.UK guidance on when you need a specified generator permit.
Frequently asked questions
How many kW is a 150 kVA generator?
On a three-phase set at a 0.8 power factor, 120 kW at the 150 kVA standby rating of the Cummins C150D5, with 109 kW on its prime rating. The C170D5 and C170D5Q give 136 kW standby and 124 kW prime.
What can a 150 kVA generator power?
The essential services of a food factory, school or college, large farm or warehouse, with large motors starting in sequence and about 20% headroom kept in reserve.
How much diesel does a 150 kVA generator use per hour?
On the Cummins C170 D5 datasheet, 12.1 litres an hour at 25% prime load, rising to 36 litres an hour at full prime load. The C150D5 page lists 31.2 litres an hour at full prime load.
Why are 150 kVA and 170 kVA generators in the same category?
Because the category groups sets in the same size band. The C150D5 is 150 kVA standby and 136 kVA prime, while the C170D5 and C170D5Q are 170 kVA standby and 155 kVA prime. Always check the kW on the prime rating.
How long will a full tank last on a 150 kVA generator?
On the C170D5 with a 448-litre tank, about 12.4 hours at full prime load and 22.4 hours at half load. The C170D5Q has a 400-litre tank, which gives about 10.8 hours at full prime load.
Is 150 kVA enough, or do I need 200 kVA?
If your realistic running load stays under about 87 kW on the C150D5 or 99 kW on the C170 sets, 150 kVA is usually enough. Above that, or if your average load approaches 70% of prime, look at 200 kVA.
Conclusion
A 150 kVA generator suits food factories, schools, large farms and warehouses, delivering 109 kW to 124 kW on its prime rating depending on the model. Check the prime kW, start big motors in sequence, check your average load against 70% of prime and leave a sensible margin.
> Talk to a real person: Global Generators is an authorised Cummins reseller and an authorised Grupel and Pramac dealer, with new diesel generators in stock for UK delivery and export. Browse the stock list, then contact our team on +44 1302 700200 or at enquiries@global-generators.com and we will help you match a set to your load.